Revetment works are proposed to take place over 5 months along the River Lagan for a distance of 184m moving a safety scaffolding 50m at a time to protect the work force working on the existing dilapidated Quay wall. The element of this work within the marine area, the erection of Scaffolding, is designed and built to support a soffit shutter that rests on the existing revetment wall, this scaffolding is built off the existing sloping rock armour.
Reference: ML2025001
Project Type: construction
Location: Coordinates: 184 m along the River Lagan
shore (between 54°36'25.6"N 5°54''51.6"W to 54°36'29.4"N 5°54'46.1"W)
Project Description: Revetment works, River Lagan Enbankment
Applicant: Graham Construction
Status: Under Consideration
Applied: 29/01/2025
Licence Start Date:
Licence End Date:
Documents
- Application Form - ML2025001
- Environmental Statement - ML2025001
- HRA - ML2025001
- Environmental Management - ML2025001
- Ecological Statement - ML2025001
- Site Plan - ML2025001
- Site Layout - 2025001
- Planning Decision Notice - ML2025001
- Precast Method Statement - ML2025001
- Quay Wall Structure - ML2025001
- Scaffolding Risk Assessment - ML2025001
- Application Supporting Information Summary - ML2025001