Construction of 10m of 200mm PVC, outfall pipe at a rock armour on Portavogie Bay Beach adjacent to Portavogie Harbour flowing to Irish Sea. Follow pipe laying works along New Harbour Road. Removal of large stones/rock armour along beach. Lay new sections of pipe encased in 200mm in-situ concrete surround. Reinstatement of large stones/rock armour around new pipe.
Reference: ML2026059
Project Type: Construction
Location: Irish Grid Reference: J 66176 59396
Latitude: 54.455986
Longitude: -5.4380329
Project Description: AtkinsRéalis are laying a new surface water sewer on New Harbour Road, Portavogie on behalf of NI Water. This will discharge 10 l/s into The Irish Sea via a new outfall pipe to serve a proposed 3G pitch development on New Harbour Road, Portavogie.
The works will include construction of 10m of 200mm PVC, outfall pipe at a rock
armour on Portavogie Bay Beach adjacent to Portavogie Harbour flowing to Irish
Sea.
The proposed outfall pipe will include 200mm of concrete surround for protection
and anchoring. The work will involve the removal and reinstatement of the rock
armour to existing condition.
Applicant: NI Water
Status: Under Consideration
Date Issued:
Licence Start Date:
Licence End Date: