Marine Construction Licence - Belfast Harbour Pontoon Reconfiguration - ML2025013
Date published:
Last updated:
The proposed works comprises the installation of 7 no. pontoon restraint piles to better restrain the pontoons and reduce the movement during storm events. Following installtion of the restraint piles, the layout of the existing pontoons will be re-configured and 2 no. additional walkway pontoon units (11.5m x 2.5m) and 2 no. additional finger pontoons installed
- Reference: ML2025013
- Project Type: Construction
- Location: Coordinates:
- 54° 36’ 21.60"N, -5° 54’ 47.32"W
- 54° 36’ 20.05"N, -5° 54’ 49.40"W
- 54° 36’ 19.45"N, -5° 54’ 48.10"W
- 54° 36’ 17.45"N, -5° 54’ 50.71"W
- 54° 36’ 17.15"N, -5° 54’ 50.00"W
- 54° 36’ 16.56"N, -5° 54’ 47.91"W
- 54° 36’ 19.89"N, -5° 54’ 43.50"W
- Project Description:
proposed works will comprise the following activities:- Procurement and delivery to site of 7 No. steel piles (approximately 508mm diameter and 20m length).
- Mobilisation of marine plant and piling plant (Jack-Up Barge, Piling Hammer, Crane).
- Removal and temporary storage of existing pontoon units to facilitate installation of restraint piles.
- Pitching and driving of steel piles at proposed locations.
- Reinstating existing pontoon units into new layout and installing new pile brackets around restraint piles.
- Installing new pontoon units and installing pile brackets around restraint piles.
- Demobilisation of marine plant and piling plant from site.
- Applicant: Belfast Harbour Commissioners
- Status: Issued
- Applied: 11/03/2025
- Licence Start Date: 05/09/2025
- Licence End Date: 04/09/2026